Massey et al.v.Duke Builders, Inc.
After a fire destroyed John and Stephanie Massey’s home, they hired Duke Builders to rebuild it, paying project costs and a contractor’s fee as work was completed. After a dispute halted construction, Duke filed a ,107 materialmen’s lien that included ,413 in anticipated profit on unfinished work. The Georgia Supreme Court affirmed the Court of Appeals: Georgia’s lien statute covers amounts due for work performed, not expected profits on future work. Including those nonlienable profits did not invalidate the entire lien; the lien remains enforceable for amounts properly due. The trial court must determine that amount and may direct amendment removing the unearned profits, though amendment is not required in every case. Any contract damages Duke may recover are separate from the question of what is lienable.